Start Date - February 2008 Projected Completion Date - substantial completion in September- update as of August 26, 2009 Cost - $5.5M (Road and Drainage - $4.8M) Water - $136K, Sewer - $630K Total - $766K
Update - Water/Sewer segment systems are being added. Receive Bids - February 17, 2009 Projected Start Date - June 2009 Projected Completion Date - November 2010 Cost - $7M (Road and Drainage - $4.9M) Water - $370K, Sewer $1.4M Total Completed - 72.92%
Final Design Phase I: 99% complete Phase II: 60% complete Projected Start Date - January 2010 Projected Completion Date - January 2012 Estimated Cost - $12.3M Phase I - Sale to McNeese - $4.6M Phase II - McNeese to Country Club - $7.68M
Fournet to Kathryn Final Design - Projected Start Date- TBA Estimated Cost $12.5M