Highway 385 Multi-Use Trail

Project Name Highway 385 Multi-use Trail              
Project Type Enhancement
Location
Within the State Highway 385 right-of-way:  begin on Ryan Street at the Pithon Coulee Bridge, north to the intersection of Clarence; west to the intersection of Clarence & Lakeshore Drive & north to the intersection of Broad and Lakeshore Drive.
Project Description Project will provide improved pedestrian access with special paving intersections, sidewalks and crosswalks, street trees, decorative lighting, landscape areas, rest area landings and site furniture.  City will provide costs including A&E, inspections, testing, surveys, etc. by DW Jessen.
A&E Environmental Resources Management
Funding Source(s) Bond 5% match plus fees, inspections, testing
Contractor TBA
AFC/Estimated Cost 700,000
Bid
TBD- DOTD bid process
Advertisement Date TBD
Receive Bids TBD
Council to Award DOTD will monitor this project
Pre Construction Meeting TBD
NTP Date TBD
Estimate For Completion
TBD
Contact
Lori Marinovich, Downtown Development Executive Director
337-491-1429
   
 
This is a competitive transportaion enhancement grant that will be designed by the City and constructed / bid by the DOTD.  Dates will be determined by DOTD bid process.
Environmental review initiated February complete mid March 2011.
Schematic Design Phase as of March 21, 2011
   
   
   
   
   
   
   
   
   
   
   
   

Published: 2009-10-08