| Project Name |
Gateway- Pithon Coulee Hurricane Surge Protection Improvements |
| Location |
SW corner of Bord du Lac and Lakeshore Drive (Lakeshore Investments LLC Tract), Bord Du Lac Drive Roadway, and corner of Bord Du Lac Park |
| Project Type |
Enhancement |
| Project Description |
This project will include elements to establish a levee for protection from a surge caused by hurricane activity. |
| A&E |
DW Jessen and Assoc. |
| Funding Source |
Bond |
| Estimated Cost/AFC |
$685,000 |
|
Contractor/Bid |
HD Truck and Tractor/$556,406.90 |
| Advertisement Date |
June 25, 2010 |
| Bid Receipt |
July 20, 2010 |
| Bid Award |
August 4, 2010 |
|
Pre-Construction Meeting |
August 19, 2010 |
| Notice to Proceed |
September 3, 2010
Closure for Bord Du Lac Drive is expected to last from September 15 through January 2011 from Millenium Park to Lakeshore Drive. |
| Projected Completion |
April 2011 |
| Construction Documents |
|
| Contact |
Lori Marinovich, Executive Director
Downtown Development
337-491-1292
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|