Gateway-Ryan Street Pithon Coulee Bridge Replacement - DOTD Enhancement back  
Date of Record: October 8, 2009

Project Name Gateway- Ryan Street Pithon Coulee Bridge Replacement - DOTD Enhancement
Project Type Enhancement
Location Ryan Street at Pithon Coulee south of Clarence Street Intersection with Ryan Street
Project Description
This project will include elements to enhance the gateway at Pithon Coulee Bridge heading north to the intersection of Clarence Street that may include architectural pylon structures, special paving, decorative lighting with banners, landscaping and way-finding signage.  DOTD will be participating in this project.  It will be divided into the following phases:
Phase I:  LA DOTD Ryan Street-Pithon Coulee Bridge Replacement $288,000.00 (80/20 DOTD=$230,400/City=$57,600)
Phase II:  DDA Ryan Street Gateway (City Funds)
 
A&E Randy Goodloe, AIA, AICP/DW Jessen and Assoc.
Funding Source DOTD and City Funds
Estimated Cost
$1.25 Million
Enhancement portion = $306,916.42/city share = $61,383.28
Contractor/Bid JD Bailey
Advertisement Date DOTD controlled
DOTD Receives Bids
March 10,2011
DOTD Contract Period Estimated at 160 working days.
Pre-Construction Meeting April 2011
Notice to Proceed
 
Estimated at June 1, 2011
Projected Completion
TBD - This is a DOTD Project.  Dates and Construction are managed by DOTD.  Project Number is 195-04-0026,  http://www.dotd.lagov/lettings/lets8220.asp
Contact
Lori Marinovich, Downtown Development
                       Executive Director
                       337-491-1429