This project consists of reconstruction and/or improvement of existing playground facilities, including construction of pavilions to cover playground equipment and parental/guardian seating areas; landscaping of playground areas at seven city parks. Parks included are Martin Luther King Park, Lock Park, University Park, Buddy Prejean Park, Bellard Park, LaGrange Soccer Park, and Wiley B. McMillan Park. Contractor is Lewing Construction.
|
Park Name |
Martin Luther King Park |
|
Location |
2009 North Simmons Street |
|
Project Description |
Relocate playground next to gymnasium, provide new
play equipment, install a shade system that adds protection
from harmful UV rays, protect the area by adding decorative
fencing and reconfigure the parking lot along with new
landscaping |
|
Cost |
$217,922 |
|
Start Date |
July 2008 |
|
Projected Completion Date |
January 2009 |
|
Current Status |
100% complete and open to public
|
|
Park Name |
Lock Park |
|
Location |
1535 Ryan Street |
|
Cost |
$161,087 |
|
Start Date |
August 2008 |
|
Projected Completion
Date |
April 2009 |
|
Current Status |
100% complete and open to public |
| Park Name |
University Park |
| Location |
1001 Central Parkway |
| Cost |
$385,400 |
| Start Date |
January 2009 |
|
Projected Completion
Date |
March 2009 |
| Current Status |
100% complete and open to public |
|
|
| Park Name |
Buddy Prejean Park |
| Location |
1601 Illinois Street |
| Cost |
$230,983 |
| Start Date |
May 2009 |
|
Projected Completion
Date |
June 2009 |
| Current Status |
100% complete and open to public |
|
|
| Park Name |
Bellard Park |
| Location |
2808 Hillcrest Street |
| Cost |
$240,211 |
| Start Date |
January 2009 |
|
Projected Completion
Date |
April 2009 |
| Current Status |
100% complete and open to public |
| Park Name |
LaGrange Soccer Park |
| Location |
200 West School Street |
| Cost |
$94,746 |
| Start Date |
February 2009 |
|
Projected Completion
Date |
March 2009 |
| Current Status |
100% complete and open to public |
| Park Name |
Wiley B. McMillan Park |
| Location |
343 Goos Street |
| Cost |
$170,671 |
| Start Date |
February 2009 |
|
Projected Completion
Date |
May 2009 |
| Current Status |
100% complete and open to public |
|
|