Gill Street Extension
Project Name | Gill Street Extension |
Project Type | Improvement |
Project Description | Includes providing safe vehicular and pedestrian linkage between the downtown and lakefront areas by integrating and connecting the existing parking lot into the new Gill Street corridor which will also promote public/private development in the lakefront area. |
A&E | DW Jessen and Assoc. |
Funding Source |
CDBG/Bond
|
Estimated Cost/AFC | $3,400,000 |
Contractor/Bid | McManus Construction Inc./$2,286,293 |
Advertisement Date | November 17, 2011 |
Bid Receipt | December 13, 2011 |
Bid Award | December 21, 2011 |
Pre-Construction Meeting | |
Notice to Proceed | April 12, 2012 |
Project Completed |
Spring 2013
|