Project Name

Lake Charles City Court

 

 

Location

 

 

 

Project Type

Improvement

 

 

Project Description

Project is being managed in conjunction with City Court Administration and will create an area to relocate City Court

 

 

A&E 
Randy Goodloe, AIA, AICP 

 

 

Funding Source
City Court Fees, City Marshal ($250K), Trust Authority ($500K), Trust Loan ($3M) 

 

 

Estimated Cost/AFC   
$4.9M  

 

 

Contractor/Bid   
Priola Construction/$4,528,000

 

 

Notice to Proceed

April 2012

 

 

Estimate for completion

24 months construction