Wastewater Projects
|
Henderson Bayou Road Sewer Locke Lane West to Dead End
Preliminary Start Date: TBD
Preliminary Completion Date: TBD |
|
Big Lake Road Sewer
Preliminary Start Date: October 2008
Preliminary Completion Date: September 2011
Bid Award: $ 3,194,011
Engineering Fee: $ 200,765
Total Cost Estimate: $ 3,394,776 |
|
5th Avenue between Bancroft Street and Prejean Street
Preliminary Start Date: TBD Preliminary Completion Date: TBD Funds Available for Construction (AFC): $540,000 Engineering Fee: $ 35,797 Total Cost Estimate: $ 575,797 |
|
Sugarloaf Sewer line
Preliminary Start Date: TBD
Preliminary Completion Date: TBD
Estimated Cost: TBD |
|
Ham Reid Rd.
Preliminary Start Date: August 2011 Preliminary Completion Date: October 2011 Bid Award: $85,000.00 Engineering Fee: $ TBD |